Closure of the temporary waste storage warehouse in the town of Gura Humorului, Suceava County

Project facts

Project promoter:
Gura Humorului City Hall(RO)
Project Number:
RO-ENVIRONMENT-0017
Status:
In implementation
Initial project cost:
€1,448,857

More information

Description

The project aims the neutralization of the area from the point of view of environmental impact.

The general objective is the improvement of the state of the environment and the reduction of the adverse effects of pollution generated by the temporary landfill. Specific objectives are: (1) Improvement of the capacity of the city to manage the risks involved by the chemical substances and dangerous waste; (2) improvement of the ecological state of the habitat which is occupied by the temporary landfill through the rehabilitation of the area.

The main activities are: A1. Mobilization of management and implementation team;  A2. Contracting and the execution of services (A.2.1. The contract for project management services; A.2.2. The contract for the elaboration of the technical design and technical assistance during the execution of works; .2.3. The contract for the verification of the technical design and for delivering Verification Reports of the Technical Design; A.2.4. The contract for information and communication services; A.2.5. The contract for financial audit services; A.2.6. The contract for site inspection)  and works;(A.2.7. The contract for works).  

The implementation of the project has, as on short term effect, the elimination of an important pollution source and rehabilitation of the area. On medium and long term, leads to the accumulation of experience for public local administration in monitoring and managing of a pollution source.

The the direct (outputs) result of the project consists in  1 temporary landfill closed and the indirect (outcomes) result of the project refers to the population benefiting from the measures to close the temporary landfill - the population of Gura Humorului City of 17.839 inhabitants.