Photovoltaic power plant for self-consumption at IPEC S.A

Project facts

Project promoter:
IPEC SA(RO)
Project Number:
RO-ENERGY-0088
Status:
Completed
Initial project cost:
€523,496
Final project cost:
€853,142

More information

Description

The main objective of the project is implementation of a photovoltaic system in order to assure electricity from renewable resources for the production process, to reduce CO2 emissions and to achieve energy independence. A feasibility study was conducted, and the results concluded that by placing a photovoltaic system on the roof of the production halls with a total area of 9.800 sq meter within the production unit.

The technical solution proposes developing a 999,635 KW photovoltaic plant with direct energy injection into the company''s own network. The photovoltaic plant will be connected to the electricity grid, without active energy injection into the distribution operator''s grid, only for own consumption purposes.  The photovoltaic panels will be placed on the roof of the two production halls. For the conversion of photovoltaic energy, 16 inverters with nominal power of 50 KW each will be used. The photovoltaic plant will produce 1.041 MWh/year for own consumption. The facility operates mainly on electricity, as in the production unit there are several equipment used in the plate production and production lines which work exclusively on electricity. The total consumption of energy of the production unit is 19.082 MWh/year. 

Key activities include:

  • Delivery of equipment and installations of PV system.
  • Internal project management.
  • Financial audit.
  • Publicity to ensure the visibility of the project.

The current project is representing an important step for the long term development strategy for increasing company''s energy independence. Its implementation reduces energy consumption from conventional sources, energy cost economy and gives a partial energy autonomy. 

Summary of project results

One photovoltaic system was set up having an installed capacity of 1 MW, number of staff trained in the project 6 employees. Regarding the expected outcomes, such as estimated annual CO2 emission reductions and  energy produced from other renewable sources in MWh/Year, will be provided by the Promoter in the Annual Project Report submitted by 15 January 2024, since the project has just finished and the results will be seen after a year after the project implementation.

Information on the projects funded by the EEA and Norway Grants is provided by the Programme and Fund Operators in the Beneficiary States, who are responsible for the completeness and accuracy of this information.