More information
Description
With this project, Pernik Municipality aims to improve the energy efficiency of three municipal buildings, which will reach the norm for buildings with close to zero energy consumption and thus contribute to achieving the main results of the Program: increased production of energy from renewable sources; improved energy efficiency in buildings; increased expert capacity in the field of energy management. The prepared investment projects envisage the implementation of the following energy saving measures:1. For the building of the VI High School "St. St. Cyril and Methodius": Insulation of external walls; Roof insulation; Insulation of the floor; Replacement of windows; Heating measures; Photovoltaic power plant; Lighting measures2. For Gym building: Insulation of external walls; Roof insulation; Replacement of windows; Heating measures; Ventilation measures; Photovoltaic power plant; Lighting measures3. For the building of Kindergarten-15 "Raina Knyaginya": Insulation of external walls; Roof insulation; Replacement of windows; Heating measures; Measures on BTV; Photovoltaic power plant. The project also envisages the exchange of experience and knowledge with a donor partner. The project will be implemented in partnership with an organization from Norway - IDN Research, with the necessary experience in the field of energy efficiency management.
Summary of project results
Poor energy efficiency of buildings and high costs.
1. For the building of the VI High School "St. St. Cyril and Methodius": -Insulation of external walls -Roof insulation -Insulation of the floor -Replacement of windows -Heating measures -Photovoltaic power plant -Lighting measures
2. For Gym building: -Insulation of external walls -Roof insulation -Replacement of windows -Heating measures -Ventilation measures -Photovoltaic power plant -Lighting measures
3. For the building of Kindergarten 15 "Raina Knyaginya": -Insulation of external walls -Roof insulation -Replacement of windows -Heating measures -Measures on BTV -Photovoltaic power plant
As a result of the project implementation the following main results are achieved: - 2319 t CO2 / g achieved emission savings; - 1965 MWh / y achieved energy savings; - 197,448 EUR / year achieved money savings; The main target group of the project, which will be affected by the effect of the achieved results, are 1061 people - children, students, staff, visiting these buildings daily. All residents of Pernik Municipality will be positively affected by the results of the project, as the measures for increased energy efficiency of public buildings lead to the creation of a better aesthetic and ecological living environment.
Summary of bilateral results
Improved bilateral cooperation with interested stakeholders in the field of energy efficiency to present good practices and future development of the city and the municipality in this regard.